Catskill Main Street Construction: What the Final Paving Changes

The paving crews on Catskill's Main Street this week are doing the last part of the job. They are also working on the part residents will look at for the next few decades. According to the Village of Catskill's notice for the week of October 19, this paving is the milestone that ends major construction. Most of the money behind that milestone went into things nobody will ever see.

Through Friday, October 23, Main Street has no parking from Thompson Street to Dutchman's Landing between 6 a.m. and 7 p.m., on both the odd and even sides. Cars left in the work zone will be towed at the owner's expense. The village is pointing drivers to the nearby parking lots.

Seventy cents of every dollar went underground

The Main Street portion of the project cost about $7.6 million. Village Board President Natasha Law broke the figure down in a statement to CBS6:

Piece of the work Cost Where it ends up
Water $2,395,727.91 Below the street
Sewer $2,918,633.74 Below the street
Streetscape, via the Downtown Revitalization Initiative grant About $2.3 million Sidewalks, curbs, trees, lights, meters

Water and sewer together come to about $5.3 million. That's roughly 70 percent of the Main Street budget, spent on mains, lead service line replacement and getting rid of combined sewer overflows. Those overflows can send untreated sewage into local waterways during heavy rain. The Times Union reported that the village put three major upgrades into one project so it wouldn't have to dig up Main Street several times.

The new sidewalks, trees and streetlights, the parts a resident will notice on a Saturday walk, come from the smallest line in the table. Law called the whole thing "a once-in-a-lifetime project fully funded by grants secured by the Village Board." She also described Main Street as one phase of a larger clean water, drinking water and downtown revitalization effort worth about $30 million, with planning and public review going back to 2022.

Why it took two construction seasons

The underground work explains the timeline. Here is the sequence Law gave CBS6:

  1. May 2025: Groundbreaking on Phase 1. Crews replaced water and sewer lines, removed combined sewer overflows and pulled out lead service lines.
  2. November 2025: Everything was patched for the winter.
  3. End of March 2026: Digging started again and moved from Church Street up to Summit Avenue.
  4. Late May 2026: The full scope of underground water and sewer work was done. Central Hudson then said it needed to install new major gas lines, so that work came next.
  5. Late May 2026: The streetscape phase began, the last phase of the Main Street project.

Some of the delays came from the street's age. The village was established in 1806, and Law said crews ran into infrastructure going back that far, including historic tunnels and old wooden water lines. "It has been a very interesting process," she told CBS6.

The finish line has moved more than once. On September 25, the Times Union reported that Law expected the work to wrap up in mid-October. A day earlier, CBS6 had reported completion by the end of October. By the village's October 16 update, crews were still pouring curbs and sidewalks from Phos to Greene Street on the west side and from Bridge to Greene on the east side. They were also doing new sewer work from Hot Yoga south to Bridge Street. The update ended with "lots of cleanup for the weekend and to prepare for paving next week."

What the street looks like when the cones leave

On the surface, the village is replacing about 85 percent of downtown sidewalks and curbing to meet full Americans with Disabilities Act compliance. The work also adds pedestrian bump-outs, new street lighting and 49 new trees. Over the summer, many doorways sat about four inches above the torn-up sidewalk. Law told CBS6 that gap was a temporary stage, and that final paving, curbing and poured concrete would bring the grades back up to meet entrances, walkways and driveways.

For anyone who has walked Main Street in the past 18 months, that may be the biggest change. A storefront step that used to need a temporary ramp should now open onto level concrete.

The meters are the last piece, and they're tangled in a trade dispute

The new parking meters will take both coins and cards, according to Law's statement. Of everything in the project, they are the item most likely to change how people run errands downtown, and they're the piece whose timing was least certain when the village last reported on them.

HudsonValley360 and the Daily Gazette reported in late September that US–Canada tariffs had hit the poles the meters mount on. The pole price rose $6,563, from $13,125 to $19,687.50, which pushed that item over the state's allowed budget. On the recommendation of MacKay Meters, the village was turning to a local company for the poles, and as of that report it had not signed a contract for them. The meters themselves would still come from Canada. Law said the switch also helps the project meet a state rule that at least 30 percent of grant-funded work go to minority- or women-owned businesses.

If the new pole quote goes over grant specifications, the village was ready to keep the old poles, which Law called "a little beat up." "Paint will bring them back to life," she said. In that report, she also said paid parking might not come back until a short time after the rest of the project is done. "I'm sure no one will mind," she added.

Once paid parking does return, the village's posted rules have metered enforcement Monday through Saturday, 9 a.m. to 5 p.m. Sundays and legal holidays are exempt. The village hasn't published the new rates yet.

The shops that bet on the finished street

The finished street is a payoff some Main Street owners have been planning around for months. In the Times Union's September report, Tom Illari, who owns Catskills Collectibles at 386 Main Street, said he had leased the shop next door so he could expand. "I'm investing in the end product here, in what Main Street is going to be like," he told the paper. "This stuff needed to be done, and there's never a convenient time to do it."

In the same story, Kira Goldfarb, owner of the cat-themed gift shop Cat on the Corner at 362 Main Street, called the stretch "a bumpy ride, literally." She also said, "It will be beautiful when it's done, and hopefully next summer will be more pleasant."

One business opened in the middle of the project. Chronogram reported in late January 2026 that Loomie's Luncheonette had just opened at 466 Main Street. That was during the winter pause, after the 2025 digging had been patched over and before crews came back in March. Across the street at 473 Main, Catskill Chocolate Co. sells handmade chocolates, espresso, desserts and gelato. NEWS10 featured it in May.

Those two storefronts matter for the next date on the calendar.

November 6, between the chocolate shop and the luncheonette

The village is marking the finished street with a First Friday Fall Festival and Main Street Revitalization Ribbon Cutting on Friday, November 6, from 5 to 8 p.m. The ribbon cutting is set for 5:30 at the head of Main Street, between Catskill Chocolate Co. and Loomie's Luncheonette. Main Street will be closed from upper Main and Water Street to the red light from 5 to 9 p.m.

The listing includes:

  • Live music from Lex Grey and The Urban Pioneers
  • Balloon animals from Mr. Twisty
  • A Puppy Pub Crawl
  • A pumpkin rolling contest
  • A silent disco
  • 50/50 raffles
  • Merchant passports and swag bags. Buying a signature drink enters your name in a door-prize drawing for a merchant gift card
  • Specials and discounts at merchants and restaurants

It's also a regular First Friday, the monthly evening when Main Street businesses stay open late. The participating directory runs from Catskill Antique Market at 321 Main and Catskill Bicycle Supply Co. at 347 Main to Body Be Well Pilates at 401 Main and Bridge Street Theater at 44 West Bridge Street. After November, the next First Friday is December 4.

Main Street isn't the end of the work. Law told CBS6 that once it's finished, the village will put the next phase of the clean water work, on the east side of the village, out to bid. For daily updates through the end of the paving, the Times Union reported that the village posts next-day schedules every evening on the Village of Catskill Facebook page, the Catskill Downtown Public Improvements Facebook page and the village website. You can also call Village Hall and press 2 for a recorded update.

If you have questions about how projects like this one change the feel and value of a historic village downtown, I'd be glad to talk them through over coffee on Main Street once the cones are gone. Jocelyn Justiniano is happy to help. Let's Connect.

Work With Jocelyn

Discover everything Upstate New York has to offer with Jocelyn Justiniano. Backed by local knowledge, genuine care, and personalized guidance, she'll help you find the perfect place to call home.

Follow Me on Instagram